| Class 1 Contract |
Contract Information |
Reasons for non-disclosure
|
| Name and address of the private sector contractor |
Design 5 Architects Pty Ltd 5 Queen Street Chippendale NSW 2008 |
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
Nil |
|
| Date the contract became effective and its duration |
Start date - 13 December 2003 End date - 30 June 2010 |
|
| Particulars of the project or goods or services to be provided under the contract |
Conservation Management Plan (4th Edition) Conservation management Plan (3rd Edition) Licence Agreement |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$65,000 + GST |
|
| Description of any renegotiation provisions |
Nil |
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines |
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil |
|
| |
|
|
| Name and address of the private sector contractor |
Downer EDI Engineering Power Pty Ltd Building B, Level 4 480 Victoria Road Gladesville NSW 2111
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
Clevertronics (equipment supply) United Group (Builder)
|
|
| Date the contract became effective and its duration |
Start date - 30 December 2008 End date - 30 July 2010 |
|
| Particulars of the project or goods or services to be provided under the contract |
Upgrade of the Emergency and Exit Light System at Sydney Opera House |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$1,499,680 + GST
|
|
| Description of any renegotiation provisions |
Nil |
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender. |
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil |
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil |
|
| Particulars of any future transfer of significant assets to and from the agency |
Nil |
|
| Results of any cost-benefit analysis |
Nil
|
|
| Particulars of how risk will be apportioned, if relevant |
Nil |
|
| Particulars of any significant guarantees or undertakings between the parties |
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period |
|
| Any other key elements of the contract (see section 30) |
Any other key elements of the contract (see section 30) |
|
| |
|
|
| Any other key elements of the contract (see section 30) |
Tyco Australia Pty Limited (trading as Wormald) Unit 1, 2-8 South Street Rydalmere NSW 2116 |
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
Nil
|
|
| Date the contract became effective and its duration |
Start date - 1 January 2007 End date - 1 January 2012
|
|
| Particulars of the project or goods or services to be provided under the contract |
Maintain and service the fire protection systems at Sydney Opera House |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$600,000 |
|
| Description of any renegotiation provisions |
Nil |
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender. |
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil
|
|
| |
|
|
| Name and address of the private sector contractor |
Show Technology Australia Pty Ltd 102 Derby Street Silverwater NSW 2128
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract. |
Nil |
|
| Date the contract became effective and its duration |
Start date - 30 April 2010 End date - 30 June 2011
|
|
| Particulars of the project or goods or services to be provided under the contract |
Theatre Moving Lights Project |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$319,200 + GST |
|
| Description of any renegotiation provisions |
Nil |
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender. |
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil
|
|
| Particulars of any future transfer of significant assets to and from the agency |
Nil |
|
| Results of any cost-benefit analysis |
Nil |
|
| Particulars of how risk will be apportioned, if relevant |
Nil |
|
| Particulars of any significant guarantees or undertakings between the parties |
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period. |
|
| Any other key elements of the contract (see section 30) |
Nil
|
|
| |
|
|
| Name and address of the private sector contractor |
Technical Audio Group Pty Ltd 43-53 Bridge Road Stanmore NSW 2048
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract. |
Nil |
|
| Date the contract became effective and its duration |
Start date – 1 April 2010
End date – 30 June 2011 |
|
| Particulars of the project or goods or services to be provided under the contract |
Theatre Audio Consoles Upgrade Project |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$359,367 + GST |
|
| Description of any renegotiation provisions |
Nil |
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender. |
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil |
|
| Particulars of any future transfer of significant assets to and from the agency |
Nil |
|
| Results of any cost-benefit analysis |
Nil |
|
| Particulars of how risk will be apportioned, if relevant |
Nil |
|
| Particulars of any significant guarantees or undertakings between the parties |
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period |
|
| Any other key elements of the contract (see section 30) |
Nil |
|
| |
|
|
| Name and address of the private sector contractor |
Jands Pty Ltd 40 Kent Road Mascot NSW 2020
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
Nil |
|
Date the contract became effective and its duration |
Start date - 1 July 2010 End date – 30 June 2011 |
|
| Particulars of the project or goods or services to be provided under the contract |
Lighting Console Upgrade |
|
| Estimated amount payable to the contractor and any allowable variations to that amount |
$594,764 + GST |
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil
|
|
| Particulars of any future transfer of significant assets to and from the agency |
Nil |
|
| Results of any cost-benefit analysis |
Nil |
|
| Particulars of how risk will be apportioned, if relevant |
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period |
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
|
|
|
| Name and address of the private sector contractor |
Marshall Day Acoustics Pty Ltd 6 Gipps Street Collingwood VIC 3066
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
|
|
Date the contract became effective and its duration
|
Start date – 8 January 2010 End date – 8 June 2011
|
|
Particulars of the project or goods or services to be provided under the contract
|
Stage Management System Design Services
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
$250,000 + GST
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
| Description of any provisions for payment to the contractor for operational or maintenance services |
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period
|
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
| Name and address of the private sector contractor |
Show Technology Australia Pty Ltd 102 Derby Street Silverwater NSW 2128
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
|
|
| Date the contract became effective and its duration |
Start date – 1 July 2010 End date - 31 June 2011
|
|
Particulars of the project or goods or services to be provided under the contract
|
Lighting Console Upgrade at Sydney Opera House
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
$292,665 + GST
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
| Particulars of how risk will be apportioned, if relevant |
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period
|
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
|
|
|
Name and address of the private sector contractor |
Hastie Services Pty Limited (t/as Trilogy Maintenance Solutions) Unit E, 255 Rawson Street Auburn NSW 2144
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
St Hillier’s Contracting Pty Ltd 88 Cumberland Street The Rocks NSW 2000
|
|
Date the contract became effective and its duration
|
Start date – 11 October 2007 End date - 30 September 2010
|
|
Particulars of the project or goods or services to be provided under the contract
|
Western Foyer Upgrade Mechanical Services – Novated Contract
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
$328,300 + GST
|
|
Description of any renegotiation provisions
|
Nil
|
|
| Method of tendering and criteria for assessment, if appropriate |
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period
|
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
|
|
|
Name and address of the private sector contractor
|
Otis Elevator Company Pty Ltd PO Box 22 Beaconsfield NSW 2014
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
|
|
Date the contract became effective and its duration
|
Start date - 29 March 2007 End date - 30 june 2010
|
|
Particulars of the project or goods or services to be provided under the contract
|
Accessibility & Western Foyer Project – Bennelong Lift Contract
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
$588,500
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Two Bank Guarantees of 2.5% contract value. One returned on Practical Completion and one returned after Defect Liability Period
|
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
|
|
|
| Name and address of the private sector contractor |
Ove Arup & Partners Level 10, 201 Kent Street Sydney, NSW 2000, Australia
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
Nil
|
|
Date the contract became effective and its duration
|
Start date - 1 June 2006 End date - 1 June 2011
|
|
|
|
|
Name and address of the private sector contractor |
Steensen Varming (Australia) Pty Ltd
160 SAILORS BAY ROAD NORTHBRIDGE NSW 2063
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
Nil
|
|
Date the contract became effective and its duration
|
Start date - 1 June 2006
End date - 1 June 2011
|
|
Particulars of the project or goods or services to be provided under the contract
|
Standing order for the provision of consultancy services to SOH (panel services agreement)
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
Scheduled rates
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Not Applicable
|
|
|
|
|
Name and address of the private sector contractor
|
Warren Smith & Partners
1st Floor, 123 Clarence Street Sydney NSW Australia 2000
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
Nil
|
|
|
|
|
| Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract |
Nil
|
|
Date the contract became effective and its duration
|
Start date - 1 June 2006
End date - 1 June 2011
|
|
Particulars of the project or goods or services to be provided under the contract
|
Standing order for the provision of hydraulics related consultancy services to SOH (panel services agreement)
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
Scheduled rates
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
Not applicable
|
|
|
|
|
| Name and address of the private sector contractor |
State Automation Pty Limited 23-27 Fonceca Street Mordialloc VIC 3195
|
|
Details of any related company or other company the contractor has an interest in that may be involved in carrying out the contractual obligations or will receive a benefit under the contract
|
|
|
Date the contract became effective and its duration
|
Start date - 1 August 2007
End date - 1 August 2010
|
|
Particulars of the project or goods or services to be provided under the contract
|
Provision of maintenance services to the stage automation, lighting and stage machinery systems at Sydney Opera House
|
|
Estimated amount payable to the contractor and any allowable variations to that amount
|
$5,667,900
|
|
Description of any renegotiation provisions
|
Nil
|
|
Method of tendering and criteria for assessment, if appropriate
|
As per NSW Government procurement guidelines. Open Expression of Interest followed by a selective Request for Tender.
|
|
Description of any provisions for payment to the contractor for operational or maintenance services
|
Nil
|
|
Particulars of any future transfer of significant assets to and from the agency
|
Nil
|
|
Results of any cost-benefit analysis
|
Nil
|
|
Particulars of how risk will be apportioned, if relevant
|
Nil
|
|
Particulars of any significant guarantees or undertakings between the parties
|
One Bank Guarantees of 5% contract value. Returned on completion of contract
|
|
Any other key elements of the contract (see section 30)
|
Nil
|
|
A copy of the contract must also be provided
|